Gramercy Terraces - Construction update

11 May 2022

May 2022 Construction update

The construction of Gramercy Terraces in Richmond is well and truly underway on the former site of GTV-9 studios.

The structure is in full swing for Stage 1 with the slab on ground and the Level 1 suspended post tension slabs completed in March for both blocks. Level-2 suspended post tension slabs took place in early April, topping out the concrete structure for Block-F.
Block-C East end townhouses Level 3 post tension slab is due for completion mid-April, which will mark the top out of the structure for Block-C.

As the concrete structure concludes, the lightweight steel framing, structural steel and internal stud framing will follow and continue throughout April and beyond.

Construction will soon commence on Blocks-A and D1 as part of the Stage 2 works. Site establishment and design development are pushing ahead with an anticipated start in late April.

Photos courtesy of Balmain and Co.

4 Apr 2022

Welcome to the first Gramercy terraces construction update

It has been a busy start to the year with both Townhouse blocks bounding out of the ground.

Block C ((38,40 Bendigo St, 11, 13, 15, 17, 19, 21, 23 Khartoum Street) is progressing well. All the inground services were completed in early March, with the ground floor and first level slabs also complete. The formwork used to support the structure while the rest of the slabs are being poured is being erected and the moment, with the final two levels in April. The formwork team has begun stripping out the ground floor to allow the steel frames to go in and allow for the rough graduation of services throughout the building. These homes are due to be completed by late Feb 2023.

Block F (6A, 6B, 8A, 8B 10 Khartoum St) is powering along, with the ground and first level slabs also completed, with the remaining floors to be poured over the next month. The strip out of the form work will start in the second week of April, allowing for the steel frames to be installed after the Easter Break. These five homes are still on track to be completed by December 2022.